Water’s Edge

EPRO provided timely, comprehensive waterproofing and contaminant protection for challenging project, Water’s Edge

“ With the EPRO system you don’t need pre-manufactured elements to make conditions work. You have a certain flexibility with the system, but really, the best part about working with EPRO was being able to make the waterproofing system function in tricky conditions.”

says Josh Osorio, Assistant Project Manager McCarthy Building Companies, Inc

The Water’s Edge office complex is located in Playa Vista, California, a relatively new mixeduse community that unites tech companies and professional sports teams, and also houses thousands of residents. The Hughes’ Aircraft Company was once located at this site, and it was also where the legendary Spruce Goose was manufactured. Due to the fact that this formerly industrial land also happens to have both extremely shallow groundwater, and naturally occurring methane gas, it is challenging to build and protect below grade space.

Phase Three of the Water’s Edge project, appropriately called WE3, is one of the final developments in the Playa Vista area. SPR:a is the architecture firm responsible for the design of the six-story creative workspace. The project is situated two levels below grade and into the water table — the overall site is a mile from the Pacific Ocean — and is supported by a pile foundation. It was also determined that due to the presence of methane gas and groundwater, which is contaminated with chlorinated solvents, the below grade waterproofing system needed to be able to do much more than just keep water out of the structure.

To provide a proper substrate for the waterproof-ing system, the team had to go down two levels below grade. At this depth, they determined that water was still coming in from different locations across the site.

EPRO E.Protect+ was specified for the site, configured into 91,000 square feet of E.Protect+ Underslab and 30,000 square feet of E.Protect+ Shoring.

“There were a multitude of things at the site that made it complicated, from the logistics of removing the soil to the fact we had to employ the French drain system and pump out water at seven or eight separate locations at the perimeter and at the bottom,” says Josh Osorio, assistant project manager, McCarthy Building Companies, Inc.

An additional challenge arose because the foun-dation was secured in place by auger cast piles.

“There were around 1,000 piles on the site that we had to waterproof and detail around, and the water was still coming up between the concrete and the rebar,” Osorio says, “In some places, we had so much water coming through some piles that we had to apply an additional waterproofing treatment just to stop the water pressure and subsequently apply EPRO.”

Sealing to piles that will be subjected to hydro-static conditions requires flawless execution. EPRO utilized pre-fabricated boots to speed up installation and provide the extra protection and detailing needed around the piles. EPRO’s redundant field installed composite systems blend together factory-made components with those fabricated in the field, allowing the systems to adapt to many different conditions.

It was clear that EPRO’s triple redundant system was the ideal solution to simultaneously combat the high water table, methane gas, and chlorinated- solvent-impacted groundwater. Additionally, the project team appreciated the peace of mind offered through the support of EPRO’s E.Assurance no-dollar- limit warranty. McCarthy selected EPRO E.Assurance Certified Contractor Courtney Waterproofing to do the install.

“With the EPRO system you don’t need pre-man-ufactured elements to make conditions work,” says Osorio. “You have a certain flexibility with the system, but really, the best part about working with EPRO was being able to make the waterproofing system function in tricky conditions.”

Throughout the project, the EPRO team visited the site on a regular basis to supervise application and installation, and also assist the construction and design team in solving the issues that arose during the project. EPRO’s due diligence ensured that there were no major delays. Ultimately, the overall speed of installation was integral to success.

“It was our goal to help Courtney so the installation ran very smoothly, without a hitch – and this was of particular importance in this high water table environment,” says Brian Miraki, Specified Products, Inc. “The job went well because we all planned well, and during the design process we developed key details with the project team to address the most challenging and critical areas. Then at the preconstruction meeting, we worked through the project with the other trades because we did not want any surprises, and we did want a smooth installation process.”

No single material should ever be relied upon to effectively waterproof a building or protect it from ground contamination. Rely on EPRO to ensure that your building remains dry and safe.

Submit your site conditions today and simplify the process with a no obligation assessment and recommendation from EPRO or Find a Local Rep in your area.